KRERA Orders Bengaluru Developer to Pay ₹1.08 Crore for Delayed Apartment Possession

Published: November 14, 2025 | Category: Real Estate
KRERA Orders Bengaluru Developer to Pay ₹1.08 Crore for Delayed Apartment Possession

The Karnataka Real Estate Regulatory Authority (KRERA) has directed Bengaluru-based developer Golden Gates Properties Ltd to pay ₹1.08 crore in delayed interest to a homebuyer for failing to deliver possession of an apartment in Presidential Tower, one of Bengaluru’s tallest residential projects, standing 161 metres high with 50 storeys.

According to the order, the buyer had booked a luxury apartment worth nearly ₹2 crore in 2014, with a promised delivery date of 2017. However, the project, a 50-storey luxury high-rise located in Yeshwanthpur, was delayed for several years, prompting the buyer to file a complaint before the regulator.

“The Respondent is hereby directed to pay delay period interest of ₹1.08 crore calculated at the rate of SBI MCLR 2% from 2017 till 2024,” the order said. Further, the interest due from 2024 till actual delivery of possession will be calculated likewise and paid to the Complainant,” it added.

In this case, the buyer, Premlatha, entered into a sale agreement with the builder on November 29, 2014, to purchase a flat in A Block of the Presidential Tower project for ₹1.98 crore and paid ₹1.5 crore as per the payment schedule. The developer had promised possession by November 1, 2017, with a four-month grace period, but the flat has not been handed over yet. The complainant, who made all payments on time, has approached the KRERA seeking interest for the delay and directions to complete the project with pending amenities, the order said.

The KRERA order stated that the project’s registration was originally valid from July 1, 2014, to June 30, 2021, and was later extended due to COVID-19 till March 30, 2022. The promoter then applied for an extension under Section 6 of the RERA Act, which was approved until March 3, 2023.

Since the project was still not completed, the Authority granted another extension under Section 7(3) of the Act, allowing the project to continue until December 31, 2025.

The KRERA noted that the agreed possession date for the flat was 2017, with an additional grace period of four months as per the sale agreement. “The complainant paid substantial sums and complied with payment obligations, yet the possession has not been handed over to date,” it said.

KRERA said that the developer cited RERA extensions and the pandemic as reasons for the delay. “There is no documentary material placed on record showing that the complainant gave consent to vary the agreed date in the sale agreement or that a fresh agreement varying the contractual date was executed with the complainant,” the order said.

The authority also clarified that administrative extensions under RERA do not amend private contracts or exempt promoters from paying delay compensation. KRERA noted that the developer had offered the buyer a one-time concession of ₹10.5 lakh as a settlement, which the buyer was not bound to accept. The builder cited COVID-19 and force majeure for the delay, but failed to provide specific, month-wise evidence of labour or material shortages affecting the flat’s handover, it said.

A list of questions has been sent to the developer. The story will be updated if a response is received.

Stay Updated with GeoSquare WhatsApp Channels

Get the latest real estate news, market insights, auctions, and project updates delivered directly to your WhatsApp. No spam, only high-value alerts.

GeoSquare Real Estate News WhatsApp Channel Preview

Never Miss a Real Estate News Update — Get Daily, High-Value Alerts on WhatsApp!

Frequently Asked Questions

1. What is KRERA?
KRERA stands for Karnataka Real Estate Regulatory Authority. It is a regulatory body established under the Real Estate (Regulation and Development) Act, 2016, to protect the interests of homebuyers and promote transparency in the real estate sector in Karnataka.
2. Why did KRER
order the developer to pay ₹1.08 crore? A: KRERA ordered the developer, Golden Gates Properties Ltd, to pay ₹1.08 crore in delayed interest to the homebuyer because the developer failed to deliver possession of the apartment as promised in the sale agreement.
3. What was the agreed possession date for the flat?
The agreed possession date for the flat was November 1, 2017, with a four-month grace period as per the sale agreement.
4. How many times was the project’s registration extended?
The project’s registration was extended multiple times. It was initially valid from July 1, 2014, to June 30, 2021, and was extended due to COVID-19 till March 30, 2022. The promoter then applied for an extension under Section 6 of the RERA Act, which was approved until March 3, 2023. Another extension under Section 7(3) of the Act was granted until December 31, 2025.
5. What did the developer offer as
settlement? A: The developer offered the buyer a one-time concession of ₹10.5 lakh as a settlement, which the buyer was not bound to accept.