Maharashtra Tightens SRA Norms to Secure Slum Rehabilitation Dues
By GeoSquare News Desk · Published 2026-01-14
The Slum Rehabilitation Authority (SRA), the nodal agency for slum redevelopment under the Maharashtra government, has introduced stricter regulatory controls on free-sale inventory in slum rehabilitation projects. These measures are aimed at securing transit rent payments and ensuring the provision of permanent alternate accommodation (PAP) to eligible slum dwellers.
In a consolidated office order, the SRA has mandated that sale flats will be ring-fenced at the stage of issuing the Intimation of Approval (IOA), amended IOA, Letter of Intent (LOI), or revised LOI. This move is in line with earlier circulars and directions from the Bombay High Court.
Under the new framework, the executive engineer will compute the developer’s transit rent liability for a minimum period of three years at the approval stage. Based on this assessment, specific sale flats or sale areas will be identified and frozen as security. Typically, lower-floor sale flats are earmarked to ensure sufficient and easily traceable inventory.
The order mandates that all frozen flats be clearly marked on approved building plans and explicitly listed as conditions in the IOA or LOI. Details such as flat numbers, carpet or built-up area, floor level, and building identification must be specified to limit any post-approval changes or dilution of obligations.
Developers are required to submit a formal undertaking or affidavit confirming that the frozen flats cannot be sold, mortgaged, transferred, or otherwise encumbered. These restrictions will remain in place until the rehabilitation work is completed, PAP units are allotted to all eligible beneficiaries, and all transit rent and allied dues are cleared.
To strengthen enforcement, the SRA has made it mandatory to formally inform the Inspector General of Registration and the Controller of Stamps, as well as the Maharashtra Real Estate Regulatory Authority (MahaRERA), of PAP and Permanent Transit Camp (PTC) details, along with the inventory of frozen flats. Certified plans and the relevant IOA or LOI must be shared with these authorities, and frozen units cannot be marketed or booked as free-sale inventory.
Defreezing will be permitted only after full compliance, including the completion of rehabilitation, allotment of PAP units, clearance of dues, and prior approval from the deputy chief engineer of the SRA.
This move is expected to materially alter risk assessment and funding structures for lenders backing SRA projects. With a portion of free-sale inventory formally frozen and unavailable for sale, mortgage, or registration until rehabilitation milestones are met, lenders may face reduced security cover in the initial stages. This could lead banks and NBFCs to rework loan-to-value ratios, seek higher promoter equity, or demand additional collateral outside the project.
Project cash-flow modelling is also likely to come under sharper scrutiny, as sales from frozen units cannot be used to service debt in the early phases. Lenders may increasingly link disbursements to rehabilitation progress rather than construction milestones alone, while tightening escrow controls and end-use monitoring. Industry executives said the framework could also slow refinancing and take-out financing for under-construction SRA projects, with lenders factoring in longer lock-in periods before inventory becomes freely available to the developer.