MahaRERA Grants Relief to Goregaon Project Buyers Amidst Repeated Delays

Published: December 18, 2025 | Category: Real Estate Mumbai
MahaRERA Grants Relief to Goregaon Project Buyers Amidst Repeated Delays

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has issued a decisive order providing relief to 13 families affected by long-standing delays in the Arista project in Goregaon, Mumbai. The order directs Sahajanand Developers and its proprietor to execute and register agreements for sale with allottees within 60 days, signalling a firm stance on protecting buyer rights amid repeated project delays.

The Arista project, registered with MahaRERA, was initially slated for completion in December 2019 but has faced multiple postponements, first to December 2022 and most recently to December 2025. Thirteen individual complaints were consolidated for the hearing, representing buyers who had paid up to 95 per cent of their flat’s consideration without receiving possession or formal agreements. Advocate representation for several complainants highlighted the financial and emotional stress borne by buyers. An official from MahaRERA noted that consolidating complaints allowed for a comprehensive evaluation of the developer’s obligations and the impact of delay on all affected families.

Sahajanand Developers cited force majeure, including COVID-19 disruptions and administrative approval delays, as primary reasons for the protracted timeline. The promoter also contended that some buyers had defaulted on payments, while compensation claims for mental distress fell outside RERA’s jurisdiction. MahaRERA, chaired by Manoj Saunik, outlined a dual relief mechanism. Buyers opting to withdraw from the project will receive a full refund of amounts paid, excluding statutory charges such as stamp duty, within 60 days. For those continuing with their units, the developer must pay interest for every month of delay from the originally promised possession date until actual handover. The interest rate is fixed at the State Bank of India’s Marginal Cost of Lending Rate (MCLR) plus 2 per cent.

Industry experts say the order reinforces RERA’s regulatory teeth, emphasising accountability in Mumbai’s high-value residential projects. “Regulatory enforcement ensures that project delays are addressed systematically while offering buyers both financial redress and clarity on possession timelines,” said a senior real estate analyst. The case underscores broader challenges in fast-growing urban centres, where regulatory compliance, urban planning delays, and unforeseen events intersect to affect housing delivery. It also highlights the importance of contractual transparency and timely execution of sale agreements to maintain trust in real estate markets.

MahaRERA’s directive aims to balance developer and buyer interests, providing structured remedies while reinforcing the legal framework governing residential projects. For prospective homeowners, the decision serves as a reminder to verify timelines, written commitments, and dispute resolution mechanisms before investing in high-density urban developments.

Stay Updated with GeoSquare WhatsApp Channels

Get the latest real estate news, market insights, auctions, and project updates delivered directly to your WhatsApp. No spam, only high-value alerts.

GeoSquare Real Estate News WhatsApp Channel Preview

Never Miss a Real Estate News Update — Get Daily, High-Value Alerts on WhatsApp!

Frequently Asked Questions

1. What is the Arist
project? A: The Arista project is a residential development in Goregaon, Mumbai, registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA). It has faced multiple delays in completion, causing significant issues for the buyers.
2. Who is Sahajanand Developers?
Sahajanand Developers is the real estate company responsible for the Arista project in Goregaon, Mumbai. They have been directed by MahaRERA to address the delays and provide relief to affected buyers.
3. What relief has MahaRER
provided to the buyers? A: MahaRERA has directed Sahajanand Developers to execute and register sale agreements within 60 days. Buyers who wish to withdraw from the project will receive a full refund, excluding statutory charges, within 60 days. Those continuing with their units will receive interest for every month of delay.
4. What are the reasons cited by Sahajanand Developers for the delays?
Sahajanand Developers have cited force majeure events, including COVID-19 disruptions and administrative approval delays, as the primary reasons for the project delays.
5. How does this order impact the real estate market in Mumbai?
This order reinforces RERA’s regulatory authority and emphasizes accountability in high-value residential projects. It ensures that project delays are addressed systematically, providing financial redress and clarity on possession timelines for buyers.