MahaRERA Rejects Developer's Clerical Error Claim, Orders Interest for Delayed Possession in Pune

Published: April 10, 2026 | Category: Real Estate
MahaRERA Rejects Developer's Clerical Error Claim, Orders Interest for Delayed Possession in Pune

Pune, 10th April 2026: The Maharashtra Real Estate Regulatory Authority (MahaRERA) has dismissed a real estate developer’s claim that a handover deadline in a registered sale agreement was merely a “clerical error,” directing the company to pay delayed possession interest to the homebuyer.

The order, pronounced by MahaRERA Member Mahesh Pathak on April 6, 2026, involves developer Duville Estates Private Limited and its registered project, ‘Riverdale Grove’, located in Haveli, Pune.

The complainant, homebuyer Nikhil Wadaskar, purchased a flat in the project in August 2021 for a total consideration of ₹74.32 lakh, of which he had already paid ₹70.60 lakh. According to his registered Agreement for Sale, the developer was bound to hand over possession by June 30, 2024. When the developer failed to deliver the flat, Wadaskar approached MahaRERA.

In its defense, Duville Estates argued that the June 2024 date was an “inadvertent” clerical error made by its customer relations team. The developer claimed that out of 444 apartments, almost all had a committed possession date of January 31, 2026, but the first eight purchasers were accidentally given the 2024 timeline. While other buyers accepted the correction, the complainant refused.

MahaRERA firmly rejected the developer’s argument, stating that a prudent promoter cannot, at a belated stage, unilaterally disown a registered timeline. The authority noted that without a duly executed rectification deed, a unilateral claim of an “inadvertent error” is legally untenable, and the registered agreement remains binding on both parties.

Upon reviewing the contract’s clauses, MahaRERA determined the baseline possession date to be December 31, 2024. Factoring in a mandatory six-month extension granted to the real estate sector due to the second wave of the COVID-19 pandemic, the revised deadline was extended to June 30, 2025.

Since the project remains incomplete, MahaRERA ordered Duville Estates to pay interest on the actual amount paid by the buyer—excluding taxes and statutory charges—from July 1, 2025, until the date a valid Occupancy Certificate (OC) is offered. The interest is to be calculated at the State Bank of India’s Marginal Cost Lending Rate (MCLR) plus 2%.

However, in a move to ensure the ongoing construction is not jeopardized by a sudden outflow of funds, MahaRERA deferred the actual payout. The authority ruled that the accumulated interest shall be adjusted and set off against the complainant’s final outstanding dues at the time of actual possession.

Stay Updated with GeoSquare WhatsApp Channels

Get the latest real estate news, market insights, auctions, and project updates delivered directly to your WhatsApp. No spam, only high-value alerts.

GeoSquare Real Estate News WhatsApp Channel Preview

Never Miss a Real Estate News Update — Get Daily, High-Value Alerts on WhatsApp!

Frequently Asked Questions

1. What is MahaRERA?
MahaRERA stands for Maharashtra Real Estate Regulatory Authority. It is a regulatory body established under the Real Estate (Regulation and Development) Act, 2016, to protect the rights of homebuyers and promote transparency in the real estate sector.
2. What was the complaint filed by Nikhil Wadaskar?
Nikhil Wadaskar filed a complaint with MahaRERA because the developer, Duville Estates, failed to deliver the flat he purchased by the agreed possession date of June 30, 2024.
3. What was Duville Estates' defense?
Duville Estates claimed that the possession date of June 30, 2024, was an 'inadvertent' clerical error and that the correct possession date should have been January 31, 2026.
4. How did MahaRER
rule on the developer's defense? A: MahaRERA rejected the developer's defense, stating that a registered timeline cannot be unilaterally disowned and that a rectification deed is necessary to change the possession date.
5. What interest rate will Duville Estates have to pay?
Duville Estates will have to pay interest at the State Bank of India’s Marginal Cost Lending Rate (MCLR) plus 2% on the amount paid by the buyer, excluding taxes and statutory charges.