Purandar Airport Land Measurement Reaches 802 Acres, Project Gains Momentum

Published: October 03, 2025 | Category: Real Estate Pune
Purandar Airport Land Measurement Reaches 802 Acres, Project Gains Momentum

Pune - The land measurement process for the proposed Purandar International Airport has started gaining pace after the farmers, who had given their consent for land acquisition, submitted their approval letters. According to information provided by the Pune district administration, the measurement of 802 acres of land has been completed so far.

After the deadline for granting consent letters ended on September 28, the actual measurement work was initiated by the district administration from last Friday. Officials have planned to complete the entire land measurement process by October 20. Once this stage is completed, the state government will finalise the compensation package and submit proposals regarding payments and rehabilitation to the farmers. Subsequently, the process of direct land acquisition will commence.

Initially, five independent teams were appointed by the district administration for the survey work. However, to expedite the process, one additional team has now been formed. These survey teams include officers from the Revenue Department, Forest Department, Public Works Department, Agriculture Department, Maharashtra Jeevan Pradhikaran, and Purandar Lift Irrigation Scheme.

The measurement process also involves valuation of fruit-bearing trees, farm wells, and water pipelines located on the agricultural land. Officials have informed that the process has been conducted smoothly and peacefully so far.

For the airport, land will be acquired from seven villages, including Pargaon, Kumbharvalan, Ekhatpur, Munjawadi, Khanwadi, Udachiwadi, and Vanpuri. In total, around 3,000 acres of land is required for the project. “During the consent period, as many as 3,220 farmers submitted approval for acquisition of 2,810 acres of land. This translates to nearly 95% of the required land being made available through consent, clearing a major hurdle for the ambitious project,” said a senior district administration official on condition of anonymity.

The Purandar International Airport has long been seen as a crucial infrastructure development for Pune and the surrounding regions. With the land survey gaining momentum and a majority of farmers cooperating, officials are optimistic that the project will soon enter its next phase of direct acquisition and eventual construction.

Stay Updated with GeoSquare WhatsApp Channels

Get the latest real estate news, market insights, auctions, and project updates delivered directly to your WhatsApp. No spam, only high-value alerts.

GeoSquare Real Estate News WhatsApp Channel Preview

Never Miss a Real Estate News Update — Get Daily, High-Value Alerts on WhatsApp!

Frequently Asked Questions

1. What is the current status of the land measurement process for the Purandar International Airport?
As of the latest update, 802 acres of land have been measured for the proposed Purandar International Airport. The process is expected to be completed by October 20.
2. How many acres of land are required for the Purandar International Airport?
A total of 3,000 acres of land is required for the Purandar International Airport project.
3. What is the role of the district administration in the land measurement process?
The district administration is responsible for organizing and conducting the land measurement process, including forming survey teams and ensuring the smooth and peaceful execution of the survey.
4. How many farmers have given their consent for land acquisition?
As many as 3,220 farmers have submitted their consent for the acquisition of 2,810 acres of land, which is nearly 95% of the required land.
5. What are the next steps after the land measurement process is completed?
After the land measurement process is completed, the state government will finalise the compensation package and submit proposals for payments and rehabilitation to the farmers. The next phase will involve direct land acquisition and eventual construction of the airport.