MahaRERA Dismisses Homebuyers' Delay Claims Against Nidhi Towers

Published: February 04, 2026 | Category: real estate news
MahaRERA Dismisses Homebuyers' Delay Claims Against Nidhi Towers

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has dismissed two complaints filed by homebuyers Kamal Khandelwal and Varun & Sarita Khandelwal against promoter Rajan Kumar Manchanda of the project Nidhi Towers, citing lack of supporting evidence.

The complainants had sought 12% annual interest for delayed possession of flats 201 and 601, alleging that the promised possession date of July 31, 2021, was not honoured and that possession was ultimately handed over only on September 5, 2024. One of the buyers also claimed an excess payment of Rs 68.75 lakh following a revised pricing arrangement.

The promoter, represented by Adv Anil Dsouza, Secretary of the Bar Association of MahaRERA, argued that delays were caused by disputes with an earlier developer that went to arbitration, along with pandemic-related disruptions. He also contended that the buyers had taken fit-out possession earlier and that parallel civil proceedings before the Bombay High Court had been settled. The project received its Occupancy Certificate on August 7, 2024, prior to formal possession.

Upon perusal of the record, it is evident that the respondent, via a letter dated October 10, 2021, offered the complainants a reduction of 10% on the total consideration of Rs 13,25,00,000 as mentioned in the agreement for sale dated April 18, 2018, thereby revising the consideration to Rs 11.90 crore. However, it is noted that the complainants have not placed on record any supporting material, including bank statements, cheques, or payment receipts, to prove the alleged excess payment made towards the revised total consideration of Rs 11.90 crore. In the absence of such evidence, the said contention of the complainants remains unsubstantiated and supports the case of the developer, the authority observed.

Meanwhile, holding that the institution of a suit before the Bombay High Court had not been denied by the complainants, the authority stated, 'While the developer avers that the said suit was amicably settled, no document, including consent terms or settlement agreement, has been placed on record by either party to substantiate the terms or nature of such settlement. The Authority is of the opinion that, on the basis of the documents placed on record, it is difficult to conclusively determine the issues raised in the subject complaints. Also, the absence of material evidence has created evidentiary gaps which cannot be bridged by assumptions or conjecture. Consequently, the Authority is constrained in adjudicating upon the merits of the captioned complaints on the basis of the record,' the order copy read.

The authority noted that key claims — including the alleged excess payment and the nature of the High Court settlement — were not backed by documentary proof on record. Holding that evidentiary gaps made it impossible to conclusively adjudicate the dispute, it ruled that the complaints were not maintainable.

Stay Updated with GeoSquare WhatsApp Channels

Get the latest real estate news, market insights, auctions, and project updates delivered directly to your WhatsApp. No spam, only high-value alerts.

GeoSquare Real Estate News WhatsApp Channel Preview

Never Miss a Real Estate News Update — Get Daily, High-Value Alerts on WhatsApp!

Frequently Asked Questions

1. What was the main reason MahaRER
dismissed the homebuyers' complaints? A: MahaRERA dismissed the complaints due to the lack of supporting documentary evidence from the homebuyers.
2. What were the key claims made by the homebuyers?
The homebuyers claimed delayed possession and an excess payment of Rs 68.75 lakh following a revised pricing arrangement.
3. What were the promoter's arguments in response to the complaints?
The promoter argued that delays were caused by disputes with an earlier developer and pandemic-related disruptions. He also claimed that the buyers had taken fit-out possession earlier and that civil proceedings were settled.
4. What did MahaRER
find regarding the documentary evidence? A: MahaRERA found that the complainants did not provide any supporting material, such as bank statements, cheques, or payment receipts, to prove their claims.
5. What was the final ruling of MahaRERA?
MahaRERA ruled that the complaints were not maintainable due to the lack of documentary evidence and the presence of evidentiary gaps.