Pune Metro Line 3 Successfully Completes Trial Run to Balewadi Stadium

Published: August 28, 2025 | Category: Real Estate Pune
Pune Metro Line 3 Successfully Completes Trial Run to Balewadi Stadium

The Pune Metro Line 3 has achieved another significant milestone by successfully conducting a trial run to Balewadi Stadium, coinciding with Ganesh Chaturthi. This marks a crucial step towards the project's March 2026 deadline, with 87 per cent of the work already completed. The 23.3-kilometre Line 3 project, spanning 23 stations, is being executed under a public-private partnership model between the Pune Metropolitan Region Development Authority (PMRDA) and Pune IT City Metro Rail Ltd (PITCMRL).

The trial run, which commenced from Mann Depot and extended to Balewadi Stadium, follows an earlier test in July between Mann Depot and Wipro station. Trains on this stretch operated at a controlled speed of 40 km/h, a crucial step before full-scale testing begins in the coming months. Once fully operational, Line 3 will connect Hinjewadi’s bustling IT hub with Shivajinagar, offering a direct and sustainable alternative to road travel in one of Pune’s most congested corridors.

Officials explained that the three-coach trains are designed to be fully air-conditioned, with a carrying capacity of around 1,000 passengers and a top operational speed of 80 km/h. These features, paired with modern station design, are expected to significantly cut travel time and encourage a shift from private vehicles to mass transit. The project is not only a mobility solution but also an environmental imperative. By targeting one of the city’s most traffic-clogged corridors, Line 3 is expected to reduce vehicular congestion and lower carbon emissions. For Pune, which faces rising air pollution levels and strained road infrastructure, the metro expansion aligns with broader urban goals of creating sustainable, resilient, and inclusive transport systems.

Authorities emphasized that the March 2026 completion target remains on track, with construction moving steadily despite logistical challenges. The successful trial has provided confidence that subsequent phases of testing and integration will follow without major delays. Beyond easing daily commutes, Line 3 has the potential to unlock economic growth by strengthening connectivity between residential zones, IT parks, hospitals, and educational hubs. Experts note that efficient metro connectivity often stimulates real estate growth, while simultaneously offering a cleaner and safer mode of travel to thousands of workers and students.

With Ganesh Chaturthi marking this progress, the trial run has added symbolic value, reinforcing hopes that Pune’s transport future is moving in the right direction. If completed within schedule, Line 3 will not only be a crucial infrastructure addition but also a decisive step towards greener mobility in one of India’s fastest-growing urban regions. The Pune Metro Line 3 is poised to transform urban mobility and contribute to a more sustainable and prosperous city.

Stay Updated with GeoSquare WhatsApp Channels

Get the latest real estate news, market insights, auctions, and project updates delivered directly to your WhatsApp. No spam, only high-value alerts.

GeoSquare Real Estate News WhatsApp Channel Preview

Never Miss a Real Estate News Update — Get Daily, High-Value Alerts on WhatsApp!

Frequently Asked Questions

1. What is the significance of the trial run to Balewadi Stadium?
The trial run to Balewadi Stadium is a significant milestone for Pune Metro Line 3, marking the successful operation of trains on a crucial stretch and bringing the project closer to its March 2026 completion deadline.
2. What is the total length and number of stations on Line 3?
Pune Metro Line 3 is a 23.3-kilometre project that spans 23 stations, connecting key areas such as Hinjewadi’s IT hub and Shivajinagar.
3. How will Line 3 benefit the environment and reduce traffic congestion?
Line 3 is designed to reduce vehicular congestion and lower carbon emissions by offering a direct and sustainable alternative to road travel, thereby contributing to a greener and more sustainable urban environment.
4. What is the current status of the Line 3 project?
As of now, 87 per cent of the work on Line 3 has been completed, and the project is on track to meet its March 2026 completion target, with steady construction and successful trial runs.
5. How will Line 3 impact the local economy and real estate sector?
Line 3 has the potential to unlock economic growth by strengthening connectivity between residential zones, IT parks, hospitals, and educational hubs, and it is expected to stimulate real estate growth and offer a cleaner, safer mode of travel.