Supreme Court Orders Builder to Pay 18% Interest for Delayed Possession: A Win for Homebuyers

The Supreme Court of India has delivered a landmark ruling in favor of homebuyers, directing a developer to refund a homebuyer’s money with 18 percent simple interest per annum, doubling the compensation from what was earlier granted by the consumer commission. This decision sends a strong message to the real estate sector about the importance of equitable treatment in builder-buyer agreements.

Real EstateConsumer RightsSupreme CourtBuilderbuyer DisputesInterest RatesReal EstateSep 26, 2025

Supreme Court Orders Builder to Pay 18% Interest for Delayed Possession: A Win for Homebuyers
Real Estate:The Supreme Court of India, in a significant ruling for consumers caught in builder-buyer disputes, has directed a developer to refund a homebuyer’s money with 18 percent simple interest per annum—doubling the compensation from what was earlier granted by the consumer commission. This verdict, delivered on 24 September by a bench of justices Dipankar Datta and Augustine George Masih, is expected to have wide implications for consumer rights in the real estate sector, where delays in project delivery remain one of the most common grievances.

In a sharp message to builders in the real estate world, the Supreme Court reasoned that a builder who imposes steep penalties on buyers for late payments cannot evade similar liability when they default on timely delivery of possession. Many builder-buyer agreements impose harsh terms on buyers while being lenient on builders. The top court has signalled that such one-sided clauses will not be blindly enforced.

The dispute began in 2006 when homebuyer Rajnesh Sharma booked a plot in a project by M/s Business Park Town Planners Ltd, paying over Rs 28 lakh in installments. According to the buyer’s agreement, possession was due within 24 months of approval of service plans. However, despite years of payments, Sharma did not receive possession. In April 2011, the developer invoked a contractual clause to change the location of the plot citing “changes in the layout plan” and demanded an additional Rs 2.3 lakh. By 2015, Sharma had already paid more than Rs 43 lakh. The builder charged 18 percent interest on minor delays in Sharma’s payments.

Aggrieved by the planner’s failure to allot the plot, Sharma finally terminated the agreement on 27 March 2017, sending a legal notice informing the respondent about the termination of the deal from his side and seeking a refund of Rs 43,13,212, along with a 24 percent interest per annum. Sharma also sought an additional amount of Rs 72,30,000 as compensation for the increase in the property’s value that he missed out due to not receiving the plot. Possession was eventually offered only in May 2018, more than a decade after booking, and after Sharma had already terminated the agreement and filed a consumer complaint seeking refund with interest. This offer of possession in 2018 was also conditional on the payment of a further sum of Rs 7,60,900.33, which Sharma argued included improperly charged amounts, such as GST, which was introduced in 2017, while most payments were pre-2012.

In January 2023, the National Consumer Disputes Redressal Commission (NCDRC) handled Sharma’s complaint, directing the developer to refund the principal amount with nine percent simple interest per annum, along with Rs 25,000 in litigation costs. Sharma challenged this before the Supreme Court, arguing that granting nine percent interest when the builder had charged 18 percent interest from him was “in defiance of logic and reason.” The developer, however, defended the award, stating that courts have consistently granted nine percent interest in such cases and that comparison to builder’s rate was not a valid claim without proof of “actual loss” of money due to delay in possession.

The apex court disagreed with the NCDRC, calling its award inadequate, given the decade-long delay and the builder’s own conduct. “In view of the conduct of the respondent, it cannot be permitted to escape with a nominal liability for its default, while it charged interest @18% on default committed by the appellant,” the Bench observed. The top court clarified that while the builder’s penalty rate cannot automatically serve as the benchmark in every case, equity and fairness may justify applying the same standard in this case. “Although the rate of interest charged by the builder cannot be granted to the buyer as a rule of thumb, however, in the present case, equity and fairness demands that the respondent be put to the same rigours for charging 18% interest and face consequences similar to those imposed on the appellant for default committed by him. If we hold otherwise, we will be perpetuating a manifestly wrong bargain,” the judgment authored by Justice Datta said.

The Supreme Court emphasised that compensation must always be “reasonable,” depending on the facts of each case. “Law is well settled that the amount of interest should be reasonable. What is reasonable varies from case to case. The same is to be granted considering the facts and circumstances of each case,” the Bench explained. While rejecting the builder’s argument that 18 percent would amount to a “windfall” gain for the buyer, the apex court observed that the buyer had endured a decade of harassment and anxiety due to the delay.

The ruling is not just about one buyer’s grievance. It also clarifies consumer rights principles in the real estate sector. If a builder charges a high penalty for delayed buyer payments, it cannot argue for lower liability when it defaults on timely delivery. The judgment makes clear that courts are not bound to apply nine percent interest in all cases. Instead, the rate must reflect fairness, prevailing conditions, and the conduct of the parties. The Supreme Court also balanced its reasoning by cautioning that compensation should not turn into a “windfall gain.” Proof of actual loss is a “guiding lamp” for assessing damages, but in cases of extreme delay and builder misconduct, higher rates can be justified.

For buyers, the case underlines the importance of documenting payments and agreements carefully, challenging one-sided clauses that impose unequal penalties and pursuing legal remedies if compensation awarded seems insufficient. Partly allowing Sharma’s appeal, the Bench substituted the NCDRC’s nine percent interest rate with 18 percent per annum while keeping all other directions intact. The top court ordered the developer to refund the requisite amount within two months. Summing up, the judgment stated, “Suffice it to say, there is no principle of law that interest in default charged by the builder can never be granted to the buyer.”

Frequently Asked Questions

What was the main issue in the Rajnesh Sharma case?

The main issue was the significant delay in the delivery of a plot booked by Rajnesh Sharma, despite his timely payments. The developer, M/s Business Park Town Planners Ltd, failed to deliver the plot as per the agreed timeline and imposed additional charges, leading to a legal dispute.

What did the National Consumer Disputes Redressal Commission (NCDRC) initially rule in Sharma's case?

The NCDRC initially directed the developer to refund the principal amount with nine percent simple interest per annum, along with Rs 25,000 in litigation costs.

Why did the Supreme Court increase the interest rate to 18%?

The Supreme Court increased the interest rate to 18% to reflect the builder's own conduct and the decade-long delay in delivering the plot. The court emphasized that equity and fairness demanded that the builder be held to the same standards it imposed on the buyer.

What does this ruling mean for consumer rights in the real estate sector?

This ruling strengthens consumer rights in the real estate sector by ensuring that builders cannot impose harsh penalties on buyers without facing similar liabilities. It clarifies that courts are not bound to apply a standard interest rate and must consider the facts and circumstances of each case.

What should homebuyers do to protect their rights in builder-buyer agreements?

Homebuyers should document all payments and agreements carefully, challenge one-sided clauses that impose unequal penalties, and pursue legal remedies if compensation awarded seems insufficient. It is essential to be aware of consumer rights and the legal protections available.

Related News Articles

The Future of Trump Towers in India: A Luxury Real Estate Empire
Real Estate Pune

The Future of Trump Towers in India: A Luxury Real Estate Empire

Donald Trump's connection with India is deeply intertwined with his global real estate empire, particularly through the Trump Organization's ventures in luxury residential projects.

September 2, 2024
Read Article
NRI Wins Landmark Case Against Godrej Properties, Receives Refund with Interest
Real Estate Maharashtra

NRI Wins Landmark Case Against Godrej Properties, Receives Refund with Interest

An NRI based in London has won a case against Godrej Properties, receiving a refund with interest for two canceled flats. The NRI had purchased the flats in Godrej's 'The Trees' project, but the builder canceled the booking and forfeited the advance payme

September 6, 2024
Read Article
Unlocking the Metaverse Economy: A Comprehensive Guide to Earning Money
Real Estate

Unlocking the Metaverse Economy: A Comprehensive Guide to Earning Money

Discover the various ways to earn money in the Metaverse, from virtual currencies and NFTs to virtual real estate and content creation.

October 3, 2024
Read Article
Investigations Deepen: SRA Project Dispute Under Scrutiny in Baba Siddique's Murder Case
real estate news

Investigations Deepen: SRA Project Dispute Under Scrutiny in Baba Siddique's Murder Case

Mumbai police are delving into various angles, including real estate disputes, in the murder of former minister Baba Siddique. His involvement in SRA projects has raised several eyebrows.

October 14, 2024
Read Article
Pune Municipal Corporation Issues Stop Work Notices to 158 Real Estate Developers
Real Estate Maharashtra

Pune Municipal Corporation Issues Stop Work Notices to 158 Real Estate Developers

The Pune Municipal Corporation (PMC) has issued stop work notices to 158 real estate developers for violating the Maharashtra Municipal Corporation Act and Section 54 of the Maharashtra Regional and Town Planning Act, 1966. This decision comes after a com

February 24, 2025
Read Article
Brigade and Gruhas Join Forces to Launch Rs 300 Crore Earth Fund for Proptech and UrbanTech
Real Estate

Brigade and Gruhas Join Forces to Launch Rs 300 Crore Earth Fund for Proptech and UrbanTech

Brigade and Gruhas have announced the launch of the Rs 300 crore Earth Fund, aimed at driving innovation in proptech, construction tech, real estate solutions, and sustainability.

March 19, 2025
Read Article