Plotted RERA

MAULI UPAVAN-38

MOUZA- GAWASI MANAPUR, Nagpur

MAULI UPAVAN-38 is a MahaRERA project in MOUZA- GAWASI MANAPUR, Nagpur. Registration, inventory, and location from GeoSquare records.

Total units

0

Plot area

10699.27 sqm

RERA timeline

  1. Registered16 Jul 2026
  2. Possession due31 Mar 2030
  3. Promoter last activity16 Jul 2026
Alerts

Possession timeline

IST · filed dates only

  1. Registered16 Jul 2026
  2. Proposed completion31 Mar 2030
  3. Today (IST)20 Nov 2026

Project registry facts

RERA

PP1190002601200

Status

Active Project

Type

Plotted

Registration

16 Jul 2026

Completion

31 Mar 2030

Survey / CTS

city_survey_gut_no KH.NO.45/1/A/2/61 final_plot_no - mauje GAWASI MANAPUR road_street - society -

Apartments

0

Booked units

0

Key facts

RERA number
PP1190002601200
Promoter type
Partnership
Status
Active Project
Type
Plotted
Registration date
2026-07-16
Proposed completion
2030-03-31
Survey / CTS
city_survey_gut_no KH.NO.45/1/A/2/61 final_plot_no - mauje GAWASI MANAPUR road_street - society -

Inventory

Apartments
0
Booked
0
Sold
0
Unsold
0

Location

Locality
MOUZA- GAWASI MANAPUR
City / district
Nagpur
Taluka
Nagpur (Rural)
Village
Gawasi Manapur
Street
MOUZA- GAWASI MANAPUR
PIN
441108
Plot area (sqm)
10699.27
Sanctioned FSI area (sqm)
0
Proposed built-up area (sqm)
0
Total FSI
0
Parking
786
Coordinates
21.020271800000, 79.049145000000

Building details

#detailsis availabletasks / activitycompletion percentage
1AS PER SANCTIONED LAYOUT PLANYesInternal Roads & Footpaths100
2AS PER SANCTIONED LAYOUT PLANYesWater Supply100
3AS PER SANCTIONED LAYOUT PLANYesSewerage (Chamber, Lines, Septic Tank , STP)90
4AS PER SANCTIONED LAYOUT PLANYesStorm Water Drains100
5AS PER SANCTIONED LAYOUT PLANYesLandscaping & Tree Planting50
6AS PER SANCTIONED LAYOUT PLANYesStreet Lighting100
7—NoCommunity Buildings—
8AS PER SANCTIONED LAYOUT PLANYesTreatment And Disposal Of Sewage And Sullage Water0
9—NoSolid Waste Management And Disposal—
10AS PER SANCTIONED LAYOUT PLANYesWater conservation /Rain water harvesting100
11—NoEnergy managemcnt—
12—NoFire protection and fire safety requirements—
13AS PER SANCTIONED LAYOUT PLANYesElectrical meter room, sub-station, receiving station10
14AS PER SANCTIONED LAYOUT PLANYesAggregate area of recreational Open Space0
15—NoOpen Parking—
16—No——

Construction progress

stagecompletion_percent
1—
2—
3—
4—
5—
6—
7—
8—
9—
10—
11—

Location & boundaries

East

SACTIONED LAYOUT AT KH. NO. 45/1/2 (PART)

West

30 METER WIDE D.P. ROAD

North

30 METER WIDE D.P. ROAD

South

KH.NO. 40

Litigation

Status
No

Project imagery from MahaRERA filings

Request brochure for latest renders

Developer

Developer information is not available.

MahaRERA registered project

PP1190002601200

Project details are available at maharera.mahaonline.gov.in under registered projects.

View MahaRERA registration PP1190002601200

Compliance snapshot

Last developer update on filing
16 Jul 2026
Registered on
16 Jul 2026
Last verified
16 Nov 2026

View MahaRERA registration PP1190002601200