Maharashtra Consumer Commission Resolves Goregaon Flat Redevelopment Dispute

Published: June 02, 2026 | Category: Real Estate Mumbai
Maharashtra Consumer Commission Resolves Goregaon Flat Redevelopment Dispute

The Maharashtra State Consumer Disputes Redressal Commission has partly allowed an appeal filed by a developer in a redevelopment dispute while upholding key reliefs granted to a Goregaon resident who complained of a shortfall in the area of his redeveloped flat and delay in receiving possession-related information.

Meanwhile, the State Commission has also rectified the District Commission’s order, where it had assessed the area shortfall as six sq ft instead of the actual deficient space of 2.25 sq ft.

The case was filed by Chintamani Shantaram Walawalkar in 2012, a resident of a Goregaon East-based society, Guruseva Cooperative Housing Society, against the society, its developer Kabra Associates, and project management consultant S.P. Civil Engineers Pvt. Ltd., alleging deficiency in service during the redevelopment process.

The complaint was earlier partly allowed by the Additional District Consumer Disputes Redressal Commission, Mumbai Suburban, in 2022, which held all three opposite parties guilty of deficiency in service. The District Commission directed Kabra Associates to compensate the complainant for a six sq ft shortfall in the area of the redeveloped flat at the rate agreed in the redevelopment agreement. The District Commission had also directed the developer to pay agreed rent for an additional eight months. In addition, the developer was ordered to pay Rs 5,000 towards litigation costs. However, no specific reliefs were granted against the society and the project management consultant despite the finding of deficiency in service.

According to the records, Walawalkar originally owned a 445 sq ft flat in the society. Under the redevelopment scheme, he was entitled to an additional 110 sq ft free of cost and had purchased another 165 sq ft from the developer for Rs 6 lakh, taking the promised area of the redeveloped flat to 720 sq ft.

After redevelopment was completed, Walawalkar alleged that the flat handed over to him was smaller than agreed and that the developer had failed to provide complete information regarding the Occupation Certificate and Completion Certificate. He therefore approached the consumer forum seeking compensation for the alleged area shortfall, rent, and other reliefs.

The developer disputed the allegations, contending that the flat area was in accordance with the agreement when enclosed balcony space was taken into account. It also pointed out that 37 of the society’s 40 members had accepted possession of their redeveloped flats, while the complainant continued to raise objections.

To resolve the dispute, an architect was appointed by the consumer forum to measure the flat. The architect found that the flat had a carpet area of 612.82 sq ft and enclosed balcony and wall-thickness areas measuring 104.91 sq ft, resulting in a total area of approximately 717.73 sq ft.

While hearing cross-appeals filed by both the complainant and the developer, the State Commission found that the District Commission had incorrectly assessed the extent of the area shortfall. It held that the actual deficiency was only about 2.25 sq ft and not six sq ft as earlier determined. The Commission nevertheless upheld the finding that the developer had failed to directly inform the complainant about the issuance of the Occupation Certificate and Completion Certificate and, therefore, sustained the direction requiring payment of rent for the delay period.

The State Commission dismissed the complainant’s appeal seeking enhancement of reliefs and partly allowed the developer’s appeal. It modified the District Commission’s order only to the extent of reducing the compensable area shortfall from six sq ft to 2.25 sq ft, while confirming all other directions, including payment of rent and costs.

Stay Updated with GeoSquare WhatsApp Channels

Get the latest real estate news, market insights, auctions, and project updates delivered directly to your WhatsApp. No spam, only high-value alerts.

GeoSquare Real Estate News WhatsApp Channel Preview

Never Miss a Real Estate News Update — Get Daily, High-Value Alerts on WhatsApp!

Frequently Asked Questions

1. What was the main issue in the Goregaon flat redevelopment dispute?
The main issue was the shortfall in the area of the redeveloped flat and the delay in receiving possession-related information, such as the Occupation Certificate and Completion Certificate.
2. Who were the parties involved in the dispute?
The parties involved were Chintamani Shantaram Walawalkar, the resident; Guruseva Cooperative Housing Society, the society; Kabra Associates, the developer; and S.P. Civil Engineers Pvt. Ltd., the project management consultant.
3. What did the District Commission initially rule?
The District Commission held all three opposite parties guilty of deficiency in service and directed Kabra Associates to compensate the complainant for a six s
4. ft shortfall in the flat area, pay agreed rent for an additional eight months, and pay Rs 5,000 towards litigation costs.
5. What did the State Commission find in its review?
The State Commission found that the actual area shortfall was 2.25 s
6. ft instead of six s
7. ft and upheld the finding that the developer had failed to inform the complainant about the issuance of the Occupation Certificate and Completion Certificate.
8. What was the final outcome of the dispute?
The State Commission reduced the compensable area shortfall from six s
9. ft to 2.25 s
10. ft but confirmed all other directions, including payment of rent and costs.